Zero clashes is not the standard

Coordination

Zero clashes is not the standard

24 Apr 2026 · 6 min read

Zero hard-clash is not the deliverable and it is rarely the end state. Here is the tolerance, severity and gate regime we hold a federated model to before sign-off.


Any model can reach zero hard-clashes by Friday. Loosen the tolerance, dismiss the awkward results, and the report turns green. The number that gets emailed to the client is not the number that protects the site, and on a live coordination package the gap between the two is where the money leaks out.

So the count is not the standard. The standard is the regime that produces the count, the tolerances we run, the order we run them in, and the gate a model has to clear before anyone signs it off. Here is ours.

What zero actually means

Clash tolerance is the threshold below which the model treats an overlap as noise rather than a clash. We run hard-clash detection tight: the tolerance typically sits at 5–10 mm, just wide enough to filter the hairline overlaps that come from rounding in the authoring model, and no wider. The exact band is a project decision, set by the requirements and the modelling accuracy of the elements involved, tighter where the geometry is precise, wider where it has to be. That distinction matters: a two-millimetre kiss where a fitting rounds into a slab is modelling noise; a fifty-millimetre interpenetration is a duct running through a beam. Push the tolerance up to make the first disappear and you bury the second with it. Zero hard-clash only means anything when the threshold underneath it is honest.

The clashes that cost money are soft

Two services can miss each other by a clean millimetre and still be unbuildable. The pipe clears the duct, but the installer can't get a spanner between them, or the valve they need to reach every quarter is now sealed behind a cable tray. These are soft clashes: clearance, access and maintenance-envelope conflicts where nothing physically overlaps but the space still doesn't work.

We check them against the figures that actually govern, not a rule of thumb, the maintenance access each manufacturer specifies for its plant and valves, the clearance around insulated and lagged runs, the fire-separation distances where services cross a compartment line. Those come from the manufacturer's requirements, the project specifications and the applicable standards, because the access a chiller needs and the access a valve needs are not the same number. Ceiling voids, risers and corridor zones are where these bite first, because that's where the design tolerance has already been squeezed to nothing.

A model with zero hard-clashes and no clearance regime is a model that builds beautifully once and can never be maintained.

Not every clash is equal

A raw clash count treats a structural column through a riser the same as a sprinkler head 4 mm inside a tolerance band. We don't report a count; we report a register, triaged by severity, and we close it from the top.

SeverityWhat it isAction
CriticalHard collision in primary structure or a main service runResolve before the model moves
MajorClearance or access breach that blocks install or maintenanceResolve and re-coordinate
MinorLimited-impact overlap, local fix onlyLog, fix, verify
DismissedIntentional connection or within true toleranceRecorded with a reason, never silently deleted

On a live federation the honest end state is not a zero. It is a register where every item still open has a disposition against it, and a name against the disposition. Most projects reach the gate with dismissed clashes on the sheet, and that is correct. An intentional connection where a fitting meets a slab is not a defect. A four-millimetre result inside a stated tolerance is not a defect. What makes the sheet defensible is the reason recorded next to each one and the person who accepted it. A dismissed clash with no reason recorded is indistinguishable from a clash that was ignored under deadline pressure, and that distinction, not the count, is the difference between a managed sign-off and a hoped-for one.

Order is part of the standard

We resolve by clash-set priority, not by whatever the software lists first: structure against mains, mains against branches, then detail. Hard clashes clear before clearance checks even run, because a clearance result against an element that's about to move is wasted effort. Run the passes out of order and you re-coordinate the same zone three times.

The standard is a gate, not a number

All of this lives inside the CDE, not in a one-off report. A model earns its way from Work in Progress into Shared, where the delivery team coordinates it, clashes it and checks it, and where our own approval is the last one we get to give. It reaches Published, the state anyone is allowed to build from, only when the appointing party authorises it, and a severity register closed to standard is what we put in front of them to earn that. Superseded information moves to Archived, which is what preserves the record of what site was building from, and when. The clash regime is the lock on the gate we own. The CDE states and gates themselves are covered in part 2 of our ISO 19650 guide.

WORK IN PROGRESS SHARED coordinate · clash CLASH REGIME SEVERITY = CLOSED PUBLISHED safe to build from AUTHORISED BY THE APPOINTING PARTY ARCHIVED audit trail
Four states, not three. The clash regime is the lock the delivery team owns on the way out of Shared; Published is authorised by the appointing party, and Archived keeps the record of what site built from

We test the engine, we don't trust it blind

A clash result is only as good as the geometry test behind it. Before JES trusts a single automated result, the detection engine is validated against a battery of deliberately nasty edge cases, ducts crossing pipes at the principal-axis tie, walls rotated thirty degrees in plan, elbows tilted out of the horizontal, parallel runs fifty millimetres apart that must not report. If the engine calls those correctly, the clean results are worth believing. That validation is the difference between a green report and a coordinated model.

The deliverable

So the line we hold isn't "zero clashes." It's a federated model the site can build from without raising a single RFI about something that was visible in the model the whole time. Zero hard-clash is the direction, not the receipt. The standard is everything between there and the gate. For what that regime looks like on a live multi-trade package, see the Dubai Metro Blue Line case study.